Construction schedule set for Peachtree City's 18 new pickleball courts

  • caroline9243
  • Aug 7
  • 2 min read

ree

Published August 7, 2025

I’ll dink to that! 


Peachtree City pickleballers celebrated a major step forward at today’s City Council Workshop. 


Peachtree City Mayor Kim Learnard and the City Council awarded $214,000 for the design and construction management of 18 new pickleball courts at Meade Athletic Complex located off Rockaway Road and Highway 74. 


There is also a preliminary timeline for design and construction of the courts. Site grading will begin in late October, court construction in November, and court surfacing and fencing in January. The courts then have to sit for 28 days before they can be played on, and are due to be completed in February of 2026. 


Before the design is finalized, residents will have their chance to weigh in on the details. 


“Members of the Peachtree City-Fayette Pickleball Club have tremendous expertise and have played in facilities across Georgia and in other states, so they, along with the general public, will be able to offer input on design items such as placement for bleachers, sun shades, drinking fountains, fencing between the courts and more,” Mayor Learnard said. 


Funding for the pickleball courts will come from the most recent SPLOST passed by voters in March of 2023.


Dozens of pickleball players were on hand for today’s vote and erupted into applause when the measure passed unanimously.


Peachtree City resident Michelle Bahr noted it will make the sport accessible to more players. “The important part is public pickleball courts because so many people can’t afford memberships, and we are a community that stands for doing good things for the community,” she said.


The Peachtree-Fayette Pickleball Club, which boasts approximately 700 members, has shown up in numbers to City Hall since this process began. One constant presence has been club president Lloyd Smith. 


“I want to thank the City Council…Thank you all for listening,” he said. 

Preliminary Schedule of Design and Construction 

*Timelines are subject to change based on scope selected and information uncovered throughout the design and construction process. 


Notice to proceed from City: August 8, 2025


Preliminary/Schematic Design (August 9– September 3, 2025)

User Group Meetings + Design Workshop August 19, 2025

Schematic Design Progress Check August 25, 2025

Finalize SD Design (Site Layout Final) and SD estimate September 3, 2025

Submit Concept Plan to City Planning staff to begin review September 3, 2025


Design Development (September 4 - September 19, 2025)

Plans dimensioned with lighting layout to owner September 11, 2025

DD Estimate to owner September 11, 2025

Owner Design approval September 19, 2025


Construction Documents (September 20-October 17, 2025)

Construction Plans to owner October 3, 2025

Final site plan to City Planning for review October 3, 2025

GMP to Owner October 10, 2025

Owner Final Approval October 17, 2025


Mobilization and Construction (October 22, 2025 – February 1, 2026)

Install Erosion Control October 23-24, 2025

Site Grading October 27-November 7, 2025

Court Construction November 8- November 25, 2025

Sports Lighting November 19, 2025- January 9, 2026

Court Surfacing and Fencing January 5-January 23, 2026

Punch List February 2, 2026


 
 